PERMIT #7104602-DM
215 31ST AVE, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
November 19, 2025
In Review
2 cycles
Reviews Done
February 17, 2026
Ready to Issue
February 19, 2026
Issued
February 19, 2026
Completed
May 5, 2026
Expires
August 19, 2027
90
Plan Review Days — Total
55
Plan Review Days — City Control
35
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$200,000
Type
Residential Construction
Issued
February 19, 2026
Location
Central District
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Demolition Permit Demo existing house with basement and driveway.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0025675
Review cycles
2
Plan review days
90
Days in corrections
35
Expires
August 19, 2027