PERMIT #7105821-CN

4211 A 42ND AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 28, 2025
In Review
3 cycles
Reviews Done
May 28, 2026
Ready to Issue
May 28, 2026
Issued
June 5, 2026
Completed
Expires
181
Plan Review Days — Total
104
Plan Review Days — City Control
77
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$415,514
Type
Residential Construction
Issued
June 5, 2026
Location
Columbia City

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct new two-family dwelling (S Duplex) per plan. (Establish use as one duplex and one single family residence per land use code. Construct one new two-family dwelling and one new one-family dwelling per plan. Review and processing for two records under 7105821-CN)

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1180808
Review cycles
3
Plan review days
181
Days in corrections
77
Units added
3
Units removed
1
Open Map