PERMIT #7105991-BK

83 S KING ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 10, 2025
In Review
1 cycle
Reviews Done
September 23, 2025
Ready to Issue
September 25, 2025
Issued
October 1, 2025
Completed
January 29, 2026
Expires
April 1, 2027
13
Plan Review Days — Total
13
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$500,000
Type
Commercial Construction
Issued
October 1, 2025
Location
Pioneer Square

Contractor Information

Contractor
TURNER CONSTRUCTION COMPANY
General Contractor
License TURNECC237D2

Location & Map

Project Description
Turner Construction Construct blanket permit tenant improvements to Turner Construction on the fifth floor of existing commercial building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
TURNECC237D2
Review level
Full C
Primary use
Commercial
Parcel
DV0070278
Review cycles
1
Plan review days
13
Days in corrections
0
Expires
April 1, 2027