PERMIT #7107077-CN
355 N 104TH ST, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
January 22, 2026
In Review
2 cycles
Reviews Done
April 3, 2026
Ready to Issue
April 6, 2026
Issued
April 6, 2026
Completed
April 28, 2026
Expires
October 6, 2027
71
Plan Review Days — Total
30
Plan Review Days — City Control
41
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
355 N 104TH ST, SEATTLE, WA Property
Renovation at 355 N 104TH ST Project
E&K SOLUTIONS LLC Contractor
Greenwood Neighborhood
Project Overview
Project Details
Value
$16,000
Type
Commercial Construction
Issued
April 6, 2026
Location
Greenwood
Contractor Information
Location & Map
Project Description
Autumn Bauwens: Interior alts Construct interior alterations to existing institutional building, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
EKSOLSL744C7
Review level
Full +
Primary use
Institutional
Parcel
DV0049681
Review cycles
2
Plan review days
71
Days in corrections
41
Expires
October 6, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0