PERMIT #7109922-BK

506 2ND AVE, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 3, 2025
In Review
1 cycle
Reviews Done
October 20, 2025
Ready to Issue
October 23, 2025
Issued
October 24, 2025
Completed
January 9, 2026
Expires
April 24, 2027
17
Plan Review Days — Total
17
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Downtown Neighborhood

Project Overview

Project Details
Value
$183,296
Type
Commercial Construction
Issued
October 24, 2025
Location
Downtown

Contractor Information

Contractor
AVARA CONSTRUCTION INC
General Contractor
License AVARACI824BR

Location & Map

Project Description
Construct blanket permit tenant improvements to Worktank on the 3rd floor of existing commercial building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
AVARACI824BR
Review level
Full C
Primary use
Commercial
Parcel
DV0016862
Review cycles
1
Plan review days
17
Days in corrections
0
Expires
April 24, 2027
Open official SDCI detail →
View Contractor