PERMIT #7110525-CN
903 W NEWELL ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
February 13, 2026
In Review
4 cycles
Reviews Done
May 4, 2026
Ready to Issue
May 5, 2026
Issued
May 5, 2026
Completed
—
Expires
November 5, 2027
80
Plan Review Days — Total
55
Plan Review Days — City Control
25
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
903 W NEWELL ST, SEATTLE, WA Property
Addition at 903 W NEWELL ST Project
MW BUILDS LLC Contractor
Interbay Neighborhood
Project Overview
Project Details
Value
$800,000
Type
Residential Construction
Issued
May 5, 2026
Location
Interbay
Contractor Information
Location & Map
Project Description
903 West Newell St Addition & Remodel Allow housing for a stacked dwelling unit within an existing structure, per land use code. Construct additions and substantial alterations for two-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MWBUIBL780NH
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1222301
Review cycles
4
Plan review days
80
Days in corrections
25
Expires
November 5, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0