PERMIT #7113300-CN

1517 M L KING JR WAY, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
December 31, 2025
In Review
3 cycles
Reviews Done
July 14, 2026
Ready to Issue
July 14, 2026
Issued
Completed
Expires
195
Plan Review Days — Total
108
Plan Review Days — City Control
87
Days in Applicant Control
3
Review Cycles
Next stepPlan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$399,712
Type
Residential Construction
Issued
N/A
Location
Central District

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct new west one family dwelling per plan. (Establish use as single family residences per land use code. Construct (3) new one family dwellings per plan. Review and processing for three records under 7113300-CN)

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0012202
Review cycles
3
Plan review days
195
Days in corrections
87
Units added
1
Units removed
0
Open Map