PERMIT #7113415-CN

135 32ND AVE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 5, 2025
In Review
3 cycles
Reviews Done
May 12, 2026
Ready to Issue
May 13, 2026
Issued
May 13, 2026
Completed
Expires
November 13, 2027
188
Plan Review Days — Total
49
Plan Review Days — City Control
139
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$416,000
Type
Commercial Construction
Issued
May 13, 2026
Location
Central District

Contractor Information

Contractor
FIELDTURF USA INC
General Contractor
License FIELDUI955JH

Location & Map

Project Description
Leschi Playfield Improvements Playfield improvements project to install synthetic turf and gravel base material on top of the existing asphalt playfield and add a small retaining wall.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
FIELDUI955JH
Review level
Full +
Primary use
Institutional
Parcel
DV0024620
Review cycles
3
Plan review days
188
Days in corrections
139
Expires
November 13, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →