PERMIT #7113673-CN

1409 37TH AVE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 25, 2025
In Review
1 cycle
Reviews Done
December 3, 2025
Ready to Issue
December 4, 2025
Issued
December 4, 2025
Completed
Expires
June 4, 2027
8
Plan Review Days — Total
8
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Madrona Neighborhood

Project Overview

Project Details
Value
$25,000
Type
Residential Construction
Issued
December 4, 2025
Location
Madrona

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Stabilize Bunker Garage Construct alterations to existing detached garage, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0075646
Review cycles
1
Plan review days
8
Days in corrections
0
Expires
June 4, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →