PERMIT #7116062-CN

1526 M L KING JR WAY, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
December 23, 2025
In Review
3 cycles
Reviews Done
July 14, 2026
Ready to Issue
July 14, 2026
Issued
Completed
Expires
203
Plan Review Days — Total
109
Plan Review Days — City Control
94
Days in Applicant Control
3
Review Cycles
Next stepPlan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$447,600
Type
Residential Construction
Issued
N/A
Location
Central District

Contractor Information

Contractor
Vivid Development LLC
Single Family/Duplex

Location & Map

Project Description
Construct new two family dwelling per plan. (Establish use as single family residences one with an attached accessory dwelling unit per land use code. Construct (2) new one and (1) new two family dwellings per plan. Review and processing for three records under 7116062-CN)

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0012205
Review cycles
3
Plan review days
203
Days in corrections
94
Units added
1
Units removed
1
View Contractor