PERMIT #7117761-CN
650 W CREMONA ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 30, 2026
In Review
4 cycles
Reviews Done
May 22, 2026
Ready to Issue
May 26, 2026
Issued
May 26, 2026
Completed
—
Expires
November 26, 2027
112
Plan Review Days — Total
71
Plan Review Days — City Control
41
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$100,000
Type
Residential Construction
Issued
May 26, 2026
Location
Interbay
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
650 W Cremona St - Construction Construct alterations for two-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1105986
Review cycles
4
Plan review days
112
Days in corrections
41
Expires
November 26, 2027
Existing units
0
Units added
2
Units removed
0
Sleeping rooms
0