PERMIT #7118694-CN

4213 42ND AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 28, 2025
In Review
0 cycles
Reviews Done
May 28, 2026
Ready to Issue
May 28, 2026
Issued
June 15, 2026
Completed
Expires
181
Plan Review Days — Total
181
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Columbia City Neighborhood

Project Overview

Project Details
Value
$221,369
Type
Residential Construction
Issued
June 15, 2026
Location
Columbia City

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct new one-family dwelling (S SFR) per plan. (Establish use as two duplexes and two single family residences per land use code. Construct two new two-family dwellings and two new one-family dwellings per plan. Review and processing for two records under 7105821-CN)

Additional Details

Permit Intelligence
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV1180808
Review cycles
0
Plan review days
181
Days in corrections
0
Units added
6
Units removed
1
Open Map