PERMIT #7121936-CN
800 OCCIDENTAL AVE S, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
January 8, 2026
In Review
2 cycles
Reviews Done
June 4, 2026
Ready to Issue
June 4, 2026
Issued
June 4, 2026
Completed
June 17, 2026
Expires
—
147
Plan Review Days — Total
4
Plan Review Days — City Control
143
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
800 OCCIDENTAL AVE S, SEATTLE, WA Property
Other Seattle Neighborhood
Project Overview
Project Details
Value
$25
Type
Commercial Construction
Issued
June 4, 2026
Location
Other Seattle
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct temporary alterations at Lumen Field for 2026 FIFA World Cup event (3/17 - 7/31) per plan
Additional Details
Permit Intelligence
Review level
Full C
Primary use
Commercial
Parcel
DV0066517
Related land-use permit
3043745-LU
Review cycles
2
Plan review days
147
Days in corrections
143
Units added
0
Units removed
0