PERMIT #7121956-CN
747 BROADWAY, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 28, 2026
In Review
2 cycles
Reviews Done
March 26, 2026
Ready to Issue
March 28, 2026
Issued
April 3, 2026
Completed
—
Expires
October 3, 2027
57
Plan Review Days — Total
15
Plan Review Days — City Control
42
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$350,000
Type
Commercial Construction
Issued
April 3, 2026
Location
First Hill
Contractor Information
Location & Map
Project Description
Construction Permit: TI at lvls 2 & 3 Interior tenant improvements to level 2 and level 3 of existing institutional building, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ALDRIA*202RU
Review level
Full +
Primary use
Institutional
Parcel
DV0065854
Review cycles
2
Plan review days
57
Days in corrections
42
Expires
October 3, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0