PERMIT #7127721-CN
1618 30TH AVE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
February 24, 2026
In Review
3 cycles
Reviews Done
July 23, 2026
Ready to Issue
July 23, 2026
Issued
August 1, 2026
Completed
—
Expires
—
149
Plan Review Days — Total
37
Plan Review Days — City Control
112
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1618 30TH AVE, SEATTLE, WA Property
Central District Neighborhood
Project Overview
Project Details
Value
$19,825
Type
Residential Construction
Issued
August 1, 2026
Location
Central District
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct foundation repair with helical piles to existing one family dwelling per plan.
Additional Details
Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1200007
Review cycles
3
Plan review days
149
Days in corrections
112
Units added
0
Units removed
0