PERMIT #7128233-CN

3710 S ANGELINE ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
March 17, 2026
In Review
3 cycles
Reviews Done
May 19, 2026
Ready to Issue
June 1, 2026
Issued
June 1, 2026
Completed
Expires
63
Plan Review Days — Total
50
Plan Review Days — City Control
13
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$438,254
Type
Residential Construction
Issued
June 1, 2026
Location
Columbia City

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Initial tenant improvement for a gymnasium (The Little Gym) on the first floor of a mixed-use building occupy per plan. Change of use from general retail sales and services to indoor sports and recreation per land use code. Mechanical included.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Multifamily
Parcel
DV0014117
Review cycles
3
Plan review days
63
Days in corrections
13
Units added
0
Units removed
0