PERMIT #7133298-CN
800 OCCIDENTAL AVE S, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
March 16, 2026
In Review
2 cycles
Reviews Done
April 6, 2026
Ready to Issue
April 7, 2026
Issued
April 7, 2026
Completed
June 11, 2026
Expires
July 9, 2026
21
Plan Review Days — Total
20
Plan Review Days — City Control
1
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$25,000
Type
Commercial Construction
Issued
April 7, 2026
Location
Other Seattle
Contractor Information
Location & Map
Project Description
Seahwks Annex Temp Install temporary rooftop telecommunications installation to support increased network capacity for traffic, public safety, and event operations related to the 2026 FIFA World Cup in Seattle. Equipment will be in place for FIFA matches 6/15 - 7/2, and will be removed after the event.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BCTOWCT896B5
Review level
Full +
Primary use
Commercial
Parcel
DV0066517
Review cycles
2
Plan review days
21
Days in corrections
1
Expires
July 9, 2026
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0