PERMIT #7138108-CN
800 Occidental AVE S, Seattle, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
April 14, 2026
In Review
1 cycle
Reviews Done
June 5, 2026
Ready to Issue
June 5, 2026
Issued
June 5, 2026
Completed
June 17, 2026
Expires
April 15, 2026
52
Plan Review Days — Total
24
Plan Review Days — City Control
28
Days in Applicant Control
1
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
800 OCCIDENTAL AVE S, SEATTLE, WA Property
Other Seattle Neighborhood
Project Overview
Project Details
Value
$25
Type
Commercial Construction
Issued
June 5, 2026
Location
Other Seattle
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
FIFA World Cup - 2026 Construct temporary alterations (Vendor Installations) at Lumen Field for 2026 FIFA World Cup event (6/15 - 7/6), per plan
Additional Details
Permit Intelligence
Review level
Full C
Primary use
Commercial
Parcel
DV0066517
Review cycles
1
Plan review days
52
Days in corrections
28
Expires
April 15, 2026
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0