PERMIT #7144550-CN

4567 RAINIER AVE S, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
July 15, 2026
In Review
1 cycle
Issued
Completed
Expires
2
Days in Applicant Control
1
Review Cycles
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$70,000
Type
Commercial Construction
Issued
N/A
Location
Columbia City

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct supports and install portable office trailer for commercial building (Columbia Funeral Home) and occupy for 18 months per plan.

Additional Details

Permit Intelligence
Review cycles
1
Days in corrections
2
Open Map