Inferred Project · confidence 50

Construction activity at 2028 N 77TH ST

2028 N 77TH ST, SEATTLE, WA · Green Lake

Summary

1
Permits
$90,400
Est. value
Apr 8, 2026
First activity
Apr 8, 2026
Latest activity

Cho DADU Allow detached accessory dwelling unit to existing residence, per land use code. Construct as one family dwelling, per plan.

Review timeline

Feb 2, 2026 → Apr 8, 2026
Review span
64
Plan review days (total)
47
City control days
17
Applicant correction days
3
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.