How long does Seattle permit plan review take?

Based on 3,305 permits with recorded SDCI plan-review timing. "Plan review" is the time spent in review cycles before a permit is issued.

3,305
Permits analyzed
63 days
Median review
81 days
Average review
173 days
90th percentile
1.1
Avg review cycles

Half of permits clear review in 63 days or less, but the slowest 10% take 173+ days — the gap is where projects stall.

How to read these numbers

Plan around the median, budget around the 90th percentile. The average runs higher than the median because a long tail of complex projects — structural changes, new uses, landmark review — pulls it up. And each round of city review comments resets the clock while corrections are prepared, so the review-cycles figure matters as much as raw days.

Distribution of plan-review time

0–30 days
849 · 26%
31–60 days
762 · 23%
61–90 days
485 · 15%
91–180 days
924 · 28%
181–365 days
285 · 9%
365+ days
0 · 0%

Average review time by permit type

residential
91 days · 2,405 permits
commercial
49 days · 834 permits
industrial
97 days · 54 permits
land
50 days · 12 permits

Review cycles per permit

0 cycles
3,359
1 cycle
1,115
2 cycles
1,555
3 cycles
818
4 cycles
215
5 cycles
68
6 cycles
13
7 cycles
7
8 cycles
1

Each correction cycle adds a round-trip with reviewers. Permits sit out for corrections about 27 days on average.

Slowest neighborhoods by average review time

Neighborhoods with at least 3 reviewed permits, ranked by longest average review.

145 days · 31 permits
131 days · 45 permits
111 days · 50 permits
107 days · 85 permits
105 days · 91 permits
104 days · 29 permits
103 days · 29 permits
102 days · 24 permits
98 days · 66 permits
97 days · 20 permits
97 days · 11 permits
96 days · 367 permits

Average review time by review level

Full +
65 days · 1,873 permits
Full C
113 days · 548 permits
Dependent Building
144 days · 485 permits
Unknown
32 days · 311 permits
Full
35 days · 84 permits
Field
12 days · 4 permits

Raw numbers available as JSON at /api/plan-review.