Permit pipeline

Seattle's permit pipeline, from application to completion

Every Seattle building permit moves through the same funnel — application, issuance, completion. This is where the whole pipeline stands right now, computed from public SDCI records.

What the funnel says

Of 15,814 Seattle permits with an application date in the dataset, 12,707 have been issued — an issue rate of 80%. Permits that do issue take a median of 44 days from application (average 76 days; the slowest decile takes 196 days or more).

After issuance, 43% of permits are marked complete, with a median of 140 days of construction time. Permits that never issue don't disappear from this funnel — they keep the applied count honest, which is why the issue rate is the number to watch.

Looking for ADU timelines?

Accessory dwelling unit permits have their own tracker with median application-to-issuance times, step-by-step duration breakdowns, and activity by year and neighborhood.

See the ADU & DADU permit timeline and tracker →

15,814Applied
12,707Issued
5,455Completed
80%Issue rate
44 daysMedian to issue

Pipeline funnel (all permits)

Applied
15,814
Issued
12,707 · 80% of applied
Completed
5,455 · 43% of issued

80% of applied permits reach issuance, and 43% of issued permits are marked complete.

Time in each stage

Apply → Issue
44 days · avg 76 · p90 196
Issue → Complete
140 days · avg 164 · p90 338

Median durations across 12,706 issued and 5,454 completed permits.

Median apply → issue by permit type

residential
78 days · 9,758 permits
commercial
64 days · 2,773 permits
industrial
113 days · 142 permits
land
124 days · 33 permits

Raw numbers available as JSON at /api/pipeline.