Permit pipeline

Seattle's permit pipeline, from application to completion

Every Seattle building permit moves through the same funnel — application, issuance, completion. This is where the whole pipeline stands right now, computed from public SDCI records.

What the funnel says

Of 14,917 Seattle permits with an application date in the dataset, 11,879 have been issued — an issue rate of 80%. Permits that do issue take a median of 44 days from application (average 76 days; the slowest decile takes 197 days or more).

After issuance, 43% of permits are marked complete, with a median of 143 days of construction time. Permits that never issue don't disappear from this funnel — they keep the applied count honest, which is why the issue rate is the number to watch.

Looking for ADU timelines?

Accessory dwelling unit permits have their own tracker with median application-to-issuance times, step-by-step duration breakdowns, and activity by year and neighborhood.

See the ADU & DADU permit timeline and tracker →

14,917
Applied
11,879
Issued
5,098
Completed
80%
Issue rate
44 days
Median to issue

Pipeline funnel (all permits)

Applied
14,917
Issued
11,879 · 80% of applied
Completed
5,098 · 43% of issued

80% of applied permits reach issuance, and 43% of issued permits are marked complete.

Time in each stage

Apply → Issue
44 days · avg 76 · p90 197
Issue → Complete
143 days · avg 167 · p90 345

Median durations across 11,878 issued and 5,097 completed permits.

Median apply → issue by permit type

residential
79 days · 9,136 permits
commercial
64 days · 2,579 permits
industrial
116 days · 132 permits
land
127 days · 31 permits

Raw numbers available as JSON at /api/pipeline.