The Seattle permit pipeline

Every permit travels from application to issuance to completion. Here's how many make it to each stage and how long the journey takes.

13,831
Applied
10,929
Issued
4,731
Completed
79%
Issue rate
43 days
Median to issue

Pipeline funnel

Applied
13,831
Issued
10,929 · 79% of applied
Completed
4,731 · 43% of issued

79% of applied permits reach issuance, and 43% of issued permits are marked complete.

Time in each stage

Apply → Issue
43 days · avg 76 · p90 199
Issue → Complete
146 days · avg 171 · p90 353

Median durations across 10,929 issued and 4,730 completed permits.

Median apply → issue by permit type

residential
79 days · 8,393 permits
commercial
65 days · 2,391 permits
industrial
121 days · 115 permits
land
129 days · 30 permits

Raw numbers available as JSON at /api/pipeline.