The Seattle permit pipeline

Every permit travels from application to issuance to completion. Here's how many make it to each stage and how long the journey takes.

12,920
Applied
10,127
Issued
4,450
Completed
78%
Issue rate
43 days
Median to issue

Pipeline funnel

Applied
12,920
Issued
10,127 · 78% of applied
Completed
4,450 · 44% of issued

78% of applied permits reach issuance, and 44% of issued permits are marked complete.

Time in each stage

Apply → Issue
43 days · avg 77 · p90 199
Issue → Complete
149 days · avg 175 · p90 359

Median durations across 10,127 issued and 4,450 completed permits.

Median apply → issue by permit type

residential
79 days · 7,762 permits
commercial
66 days · 2,231 permits
industrial
124 days · 106 permits
land
136 days · 28 permits

Raw numbers available as JSON at /api/pipeline.