Seattle ADU & DADU permit timeline and tracker
How long ADU and DADU permits actually take, plus every accessory dwelling unit permit across Seattle by year, neighborhood, and status. Compare attached ADUs with detached backyard cottages, and see where new small-scale housing activity is concentrating.
These are matching permit records, not a count of guaranteed completed dwellings. One property or project can have multiple related permits.
Source data updated through Nov 28, 2026.
How long does an ADU permit take in Seattle?
Detached units take longer: the median DADU runs 139 days from application to issuance against 106 days for an attached ADU. Averages run higher than medians — 134 days (ADU) and 152 days (DADU) — because a small number of long reviews pull the average up.
How long each step takes
- Application — the permit is filed with the Seattle Department of Construction and Inspections. 502 ADU and 1,532 DADU permits in this dataset have an application date.
- Review — plans go through SDCI review, including applicant correction cycles where published. 77% of applied ADU permits and 80% of applied DADU permits reach issuance.
- Issuance — the permit is issued. Median 106 days after application for ADUs and 139 days for DADUs.
- Completion — construction finishes and the permit is marked complete. 32% of issued ADU permits and 30% of issued DADU permits are marked complete, with a median of 231 days (ADU) and 285 days (DADU) from issuance.
Average application → issuance time by year
| Year | Type | Issued permits | Average days |
|---|---|---|---|
| 2024 | ADU | 60 | 82 days |
| 2024 | DADU | 186 | 89 days |
| 2025 | ADU | 207 | 127 days |
| 2025 | DADU | 738 | 156 days |
| 2026 | ADU | 119 | 173 days |
| 2026 | DADU | 296 | 180 days |
Grouped by issue date; partial years reflect records ingested so far. Years with a handful of dated permits are noisier than recent full years.
ADU and DADU permits by year
Grouped by issue date when available, otherwise application date.
Seattle neighborhoods with the most ADU activity
Recent Seattle ADU and DADU permits
| Permit | Type | Address | Neighborhood | Status | Value | Date |
|---|---|---|---|---|---|---|
| 7169246-CN | DADU | 7512 31st AVE SW, Seattle, WA | West Seattle | completed | $264K | Nov 24, 2026 |
| 7151776-CN | DADU | 11732 22ND AVE NE, SEATTLE, WA | Other Seattle | active | $240K | Nov 23, 2026 |
| 7164052-CN | ADU | 6302 MERIDIAN AVE N, SEATTLE, WA | Green Lake | active | $25K | Nov 19, 2026 |
| 7005157-CN | DADU | 212 W HOWE ST, SEATTLE, WA | Queen Anne | active | $93K | Nov 18, 2026 |
| 7135481-CN | DADU | 2517 E MARION ST, SEATTLE, WA | Central District | active | $186K | Nov 16, 2026 |
| 7121787-CN | DADU | 4041 34TH AVE S, SEATTLE, WA | Columbia City | active | $214K | Nov 16, 2026 |
| 7170626-CN | ADU | 1618 E LYNN ST, SEATTLE, WA | Capitol Hill | pending | $10K | Nov 13, 2026 |
| 7147911-CN | DADU | 3231 35TH AVE W, SEATTLE, WA | Magnolia | active | $150K | Nov 13, 2026 |
| 7160905-CN | DADU | 1018 NE 117TH ST, SEATTLE, WA | Northgate | active | $312K | Nov 13, 2026 |
| 7160904-CN | DADU | 1020 NE 117TH ST, SEATTLE, WA | Northgate | active | $312K | Nov 13, 2026 |
| 6998401-DM | DADU | 214 W HOWE ST, SEATTLE, WA | Queen Anne | active | $20K | Nov 13, 2026 |
| 7148169-CN | DADU | 7936 35TH AVE SW, SEATTLE, WA | West Seattle | pending | $240K | Nov 13, 2026 |
| 7170877-CN | DADU | 7936 35TH AVE SW, SEATTLE, WA | West Seattle | completed | $240K | Nov 13, 2026 |
| 7172007-CN | DADU | 3828 20TH AVE SW, SEATTLE, WA | West Seattle | completed | $164K | Nov 13, 2026 |
| 7148239-CN | DADU | 9255 A 8TH AVE NW, SEATTLE, WA | Greenwood | active | $229K | Nov 11, 2026 |
| 7148324-CN | ADU | 3807 47TH AVE SW, SEATTLE, WA | West Seattle | active | $150K | Nov 10, 2026 |
| 7160106-CN | ADU | 7329 14TH AVE NW, SEATTLE, WA | Ballard | active | $30K | Nov 9, 2026 |
| 7168348-CN | DADU | 8742 17th AVE NW, Seattle, WA | Crown Hill | pending | $234K | Nov 9, 2026 |
| 7170088-CN | DADU | 8742 17th AVE NW, Seattle, WA | Crown Hill | completed | $234K | Nov 7, 2026 |
| 7163915-CN | DADU | 216 NW 140TH ST, SEATTLE, WA | Broadview | active | $87K | Nov 5, 2026 |
ADU vs. DADU
ADU is the broader term for an accessory dwelling unit associated with a primary home. It can be inside, attached to, or converted from part of an existing structure.
DADU means detached accessory dwelling unit. In Seattle records it may also appear as a detached ADU or backyard cottage.
How the tracker works
Building Seattle searches public permit descriptions for explicit ADU terminology, classifies detached projects separately, and aggregates results by year and neighborhood. A permit mentioning both attached and detached units is classified as DADU.
Declared permit values and housing-unit fields are presented as reported and may be incomplete or revised during review.
Using ADU permit activity
Homeowners can see the kinds of projects moving through Seattle review. Contractors and designers can identify neighborhoods with sustained accessory-dwelling demand. Researchers can track how small-scale infill contributes to Seattle's housing pipeline.
Raw tracker data is available at /api/adu-dadu. Source records come from Seattle Department of Construction and Inspections permit data.