Inferred Project · confidence 50

Construction activity at 2540 NE 92ND ST

2540 NE 92ND ST, SEATTLE, WA · Wedgwood

Summary

1
Permits
$2,500
Est. value
May 20, 2026
First activity
May 20, 2026
Latest activity

Riedo-Murray Retrofit Construct seismic retrofit to existing single family residence, per Earthquake Home Retrofit plan set.

Review timeline

May 12, 2026 → Jun 22, 2026
Review span
7
Plan review days (total)
7
City control days
0
Applicant correction days
1
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (1)

PermitTypeValueStatusDate
7142830-CN residential $2,500 completed May 20, 2026

Participants

About this project

This project was inferred by grouping related permits at the same address. Confidence score 50/100 reflects how strongly the permits appear to belong to a single effort.