Inferred Project · confidence 50

Construction activity at 325 5TH AVE N

325 5TH AVE N, SEATTLE, WA · Belltown

Summary

1
Permits
$70,000
Est. value
Dec 17, 2025
First activity
Dec 17, 2025
Latest activity

350 Thomas St - Construction - Verizon EXPO DAS Node 12 Replace existing light pole with new light pole to include integrated small wireless antennas and equipment for minor telecommunications facility [VERIZON] on institutional campus [SEATTLE CENTER], per plan.

Review timeline

Oct 22, 2025 → Jun 18, 2026
Review span
56
Plan review days (total)
26
City control days
30
Applicant correction days
3
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (1)

PermitTypeValueStatusDate
7079128-CN commercial $70,000 completed Dec 17, 2025

Participants

About this project

This project was inferred by grouping related permits at the same address. Confidence score 50/100 reflects how strongly the permits appear to belong to a single effort.