Tomlin Foundation Repair Construct foundation repair with push piles to existing one family dwelling, per plan.

Review timeline

Feb 24, 2026 → May 26, 2026
Review span
29
Plan review days (total)
19
City control days
10
Applicant correction days
2
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.