Mechanical upgrade at 6100 6TH AVE S
6100 6TH AVE S, SEATTLE, WA · GeorgetownSummary
1
Permits
$200,000
Est. value
Oct 28, 2025
First activity
Oct 28, 2025
Latest activity
ACI Mechanical Construct alterations in NW portion of existing commercial building, per plan.
Review timeline
Sep 3, 2025 → Apr 24, 2026
Review span
54
Plan review days (total)
49
City control days
5
Applicant correction days
2
Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (1)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7095152-CN | commercial | $200,000 | completed | Oct 28, 2025 |
Participants
- BOYCE CONSTRUCTION INC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 50/100 reflects how strongly the permits appear to belong to a single effort.