New construction at 2203 AIRPORT WAY S
2203 AIRPORT WAY S, SEATTLE, WA · SoDoSummary
1
Permits
$416,242
Est. value
May 6, 2026
First activity
May 6, 2026
Latest activity
2203 Airport Way S - Construction - WSP Crime Lab - Generator Construct alterations to replace generator/pad and install site retaining wall to support new equipment between commercial buildings (WSP Crime Lab and Test Firing Range) at Airport Way Center, per plan.
Review timeline
Sep 18, 2025 → May 6, 2026
Review span
92
Plan review days (total)
23
City control days
69
Applicant correction days
2
Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (1)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7102255-CN | industrial | $416,242 | active | May 6, 2026 |
Participants
- Vets Power Electric LLC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 50/100 reflects how strongly the permits appear to belong to a single effort.