New construction at 3611 E DENNY WAY

3611 E DENNY WAY, SEATTLE, WA · Madrona

Summary

3Permits
$6,813,127Est. value
Sep 16, 2025First activity
Mar 31, 2026Latest activity

Epiphany School - Madrona Hall Classroom Renovation Construct alterations to portions of a school building to convert administrative offices to classrooms, per plans

Review timeline

Feb 28, 2025 → Mar 31, 2026Review span
16Plan review days (total)
172Applicant correction days
3Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (3)

PermitTypeValueStatusDate
7123601-CN commercial $600,000 Active Mar 31, 2026
7068981-CN commercial $500,000 Active Feb 27, 2026
7020685-CN commercial $5,713,127 New Sep 16, 2025

Participants

About this project

This project was inferred by grouping related permits at the same address. Confidence score 83/100 reflects how strongly the permits appear to belong to a single effort.