Inferred Project · confidence 50
New construction at 5901 EAST MARGINAL WAY S
5901 EAST MARGINAL WAY S, SEATTLE, WA · GeorgetownSummary
1
Permits
$200,000
Est. value
Apr 1, 2026
First activity
Apr 1, 2026
Latest activity
New Inventory Overhead Door Construct exterior alterations to existing warehouse building, per plan.
Review timeline
Feb 2, 2026 → Apr 1, 2026
Review span
58
Plan review days (total)
21
City control days
37
Applicant correction days
3
Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (1)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7123140-CN | industrial | $200,000 | active | Apr 1, 2026 |
Participants
- SKYE INDUSTRIAL INC contractor