Inferred Project · confidence 50

Renovation at 3959 NE SURBER DR

3959 NE SURBER DR, SEATTLE, WA · Other Seattle

Summary

1
Permits
$50,000
Est. value
Jul 6, 2026
First activity
Jul 6, 2026
Latest activity

Lico Front Yard Construct alterations to replace concrete driveway, gates and fences, grade for lawn and garden at north side of existing single family residence, per plan.

Review timeline

May 4, 2026 → Jul 6, 2026
Review span
59
Plan review days (total)
20
City control days
39
Applicant correction days
2
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (1)

PermitTypeValueStatusDate
7134319-CN residential $50,000 active Jul 6, 2026

Participants

About this project

This project was inferred by grouping related permits at the same address. Confidence score 50/100 reflects how strongly the permits appear to belong to a single effort.