Inferred Project · confidence 50
Renovation at 6317 14TH AVE NE
6317 14TH AVE NE, SEATTLE, WA · RooseveltSummary
1
Permits
$126,504
Est. value
Sep 2, 2025
First activity
Sep 2, 2025
Latest activity
SFR STFI Construct substantial alterations to SFR, subject to field inspection, STFI.
Review timeline
Aug 30, 2025 → Dec 4, 2025
Review span
0
Applicant correction days
0
Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (1)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7104435-CN | residential | $126,504 | completed | Sep 2, 2025 |
Participants
- RD REMODELING LLC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 50/100 reflects how strongly the permits appear to belong to a single effort.