Inferred Project · confidence 50

Tenant improvement at 534 NE NORTHGATE WAY

534 NE NORTHGATE WAY, SEATTLE, WA · Maple Leaf

Summary

1
Permits
$275,000
Est. value
Apr 3, 2026
First activity
Apr 3, 2026
Latest activity

ATI Physical Therapy Northgate Change of use from general retail sales and services to medical services, per land use code. Tenant improvement in existing commercial building at ground level, per plan. Mechanical included.

Review timeline

Jan 27, 2026 → Jul 10, 2026
Review span
64
Plan review days (total)
45
City control days
19
Applicant correction days
2
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (1)

PermitTypeValueStatusDate
7122494-CN commercial $275,000 completed Apr 3, 2026

Participants

About this project

This project was inferred by grouping related permits at the same address. Confidence score 50/100 reflects how strongly the permits appear to belong to a single effort.