Inferred Project · confidence 50
New construction at 510 6TH AVE S
510 6TH AVE S, SEATTLE, WA · Pioneer SquareSummary
1
Permits
$28,191
Est. value
Dec 1, 2025
First activity
Dec 1, 2025
Latest activity
St Paul Medical Clinic Construct alterations to replace existing security shutters and new vestibule at ground level (St. Paul Medical Clinic) of existing mixed-use building, per plan.
Review timeline
Oct 29, 2025 → Jul 7, 2026
Review span
23
Plan review days (total)
21
City control days
2
Applicant correction days
2
Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (1)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7113067-CN | commercial | $28,191 | completed | Dec 1, 2025 |
Participants
- METIS CONSTRUCTION INC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 50/100 reflects how strongly the permits appear to belong to a single effort.