Inferred Project · confidence 50

Renovation at 3951 15TH AVE S

3951 15TH AVE S, SEATTLE, WA · Beacon Hill

Summary

1
Permits
$100,000
Est. value
Mar 30, 2026
First activity
Mar 30, 2026
Latest activity

Qi Qi: Interior Alts Construct alterations to existing two-family dwelling, per plan

Review timeline

Jan 28, 2026 → Mar 30, 2026
Review span
57
Plan review days (total)
38
City control days
19
Applicant correction days
3
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (1)

PermitTypeValueStatusDate
7123547-CN residential $100,000 active Mar 30, 2026

Participants

No participants on record.

About this project

This project was inferred by grouping related permits at the same address. Confidence score 50/100 reflects how strongly the permits appear to belong to a single effort.